Active Projects
Project Description
Development of Phase 1 of the new Environmental Education center at the Emory Waters Nature Preserve. The first phase of the project includes cabins for camping, a bathhouse, pavilion and parking. Later phases include a field station building to support research activities, water access facilities, and shoreline protection efforts.
Project Consultants
Whitney Bailey Cox & Magnani, LLC
Project Status
In Design
Project Updates
Design work continues. A public meeting on the 30% design was held on November 29, 2022. A copy of the engineer's presentation and other information about that meeting can be found at the links below.
2022-11-29 - Public Meeting on the the 30% design
A Public Information Meeting will be held prior to the start of construction.
For schedule information see Department of Public Works website