Active Projects
Project Description
Water Quality and Shoreline Improvements. Design of dredging and restoration plan to address issues negatively impacting aquatic life and water quality.
Project Consultants
BayLand Consultants & Designers, Inc.
Project Status
In Design
Project Updates
Recreation and Parks held a Public Meeting on September 13, 2023 to present the 30% Schematic Design and receive input from the community. Information and the recorded meeting are linked below.
Project Description:
The project includes a new multi-sport rink for adaptive sports, five (5) new tennis courts with an air-supported enclosure, four (4) new pickleball courts, a new pavilion, expanded parking, ADA accessible walkways, reforestation, stormwater management, and other site improvements.
The project includes a new multi-sport rink for adaptive sports, five (5) new tennis courts with an air-supported enclosure, four (4) new pickleball courts, a new pavilion, expanded parking, ADA accessible walkways, reforestation, stormwater management, and other site improvements.
Project Consultants:
TranSystems, Inc.
TranSystems, Inc.
Project Status:
In Design
In Design
Project Updates:
The Departments of Public Works and Recreation and Parks will hold a Community Meeting on February 18, 2025 to present the 30% Schematic Design and receive input from residents. For schedule information see Department of Public Works website https://www.aacounty.org/public-works/engineering/capital-projects.